Implementation Plan


Implementation

TaskGoal  Start Date  Completion Target Date
  Market Research  Assess demand in off-grid communities, farms, and Indigenous nations; identify competitor gaps; survey clients  January 2nd, 2026February 3rd, 2026
  Business Setup  Choose incorporation; register with BC Registry Services; obtain electrical contractor license, wind certifications, and $1-2M insurance  February 4th, 2026March 7th, 2026
  Permits and Compliance  Comply with Streamlined Permitting Act; engage First Nations; secure certifications via BCER portal  March 8th, 2026May 9th, 2026
  Funding  Apply for ICE Fund ($500,000) or First Nations Clean Energy Fund ($50,000-$500,000); secure $100,000 in grants/loans  May 10th, 2026July 11th, 2026
  Training and Team  Train at Northern Lights College or NABCEP; hire 1-2 technicians  July 12th, 2026September 13th, 2026
  Equipment and Operations  Source 2-3 turbines from Borum Energy; lease warehouse in Fort St. John/Prince George; complete test installation  September 14th, 2026December 15th, 2026
Marketing and SalesBuild website; use social media and partnerships; generate 5-10 leads/month  December 16th, 2026March 7th, 2027

Budget Breakdown

CategoryBudget
Business Setup$2000-$5000
Permits (per project)$5000
Equipment$50,000-$150,000
Training$10,000-$20,000
Marketing/Operations$25,000-$60,000
Total$85,000-$230,000